Farm Activity Calendar

Following are activities completed / scheduled status :


SCHEDULED
Installation of 2.5 HP Motor Pump (Additional Pump for Single Value Usage)
Purchase of Power Weeder 
Electric Conversion of Power Weeder
BioFloc Fish Farming (Trial)
Fodder Crop for Rabbit & Country Chicken
Rabbit Farming
Poultry Farming (Country Chicken)


COMPLETED 
April 2020 -  Mulberry Weeding & Earthening
March 2020 -  Installation of Bio Digester FRP Septic Tank
March 2020 -  Additional Civil Work for House
February 2020 - 5.0 HP Motor Pump Installed @ Farm Pond (Removed 7.5HP)
February 2020 -  Installation of Magnetic Water Softener 
February 2020 -  Drip Lateral Rework
February 2020 -  Installation of 0.5 HP Motor for Venturi @ Fertigation System
January 2020 -  Extension of Mulberry Plantation for Valve 3 & 7
January 2020 -  Weeding for Mulberry Plantation, Apply Organic Fertiliser
January 2020 -  Pruning for Mulberry Plantation
December 2019 -  Ploughing for Mulberry Plantation
November 2019 -  Mulberry Plantation, Installing Dripper, First Pruning, First Fertiliser,  First Irrigation, Remove Weeds & Ploughing
October 2019 - Mulberry Nursery Sapling Purchase Tour
October 2019 -  Purchase of Organic Materials (Bio Fertiliser, Vermi Compost, FYM, Coco Peat & Neem Cake)
September 2019 -  Fertigation System 
September 2019 - Rain Water Harvesting for Farm House (1900 Sqft)
August 2019 -  JCB Pit Work for Mulberry Tree Plantation
August 2019 -  JCB Bund & Trench Work for Boundary
July 2019 - Initiated Canal Water Facilities
July 2019 - Field Preparation :  2nd Ploughing & Rotavator for Mulberry Plantation
June 2019 - Patta Process for Extended New Farm Land
June 2019 -  EB Connection for House
May 2019 -  Field Preparation :  Ploughing for Mulberry Plantation 
April 2019 - Installation of Fertigation System
April 2019 -  Construction of Rest Room
March 2019 -  Installation of Automated Irrigation System 
March 2019 - 7.5 HP Motor Pump Installed @ Farm Pond
February 2019 - Room for EB, Motor, Filtration, Automation & Organic Fertiliser (450 SFT) & Additional Storage Area (450 SFT)
February 2019 -  Plumbing / Irrigation System
January 2019 -  Boundary Solar Fencing
December 2018 -  10HP Solar Panel System for 2nd Borewell.
November 2018 -  Construction of House for Workers (300 SFT) & 
Storage Room (300 SFT)
October 2018 -  Internal Road / Pathway Marking
October 2018 -  1st Borewell Motor Pump Installed 
September 2018 -  2nd Borewell (Water Levels :  320 & 550 Feet)
September 2018 -  EB Takkal Connection Installed
August 2018 -  1st Borewell (Water Levels : 310 & 580 Feet)
August 2018 -  Water Diving (2nd Opinion)
June 2018 -  EB Applied (Free Connection)
July 2018 -  EB Takkal Scheme Applied (10 HP) 
June 2018 -  Trenching (Boundary)
June 2018 -  Water Diving (1st Opinion)
May 2018 -  Documents (Sale Deed, Patta, Adangal, FMB & Boundary Details by VAO)
May 2018 -  Soil & Water Test Report
May 2018 -  Land Clean Up, Levelling & 1st Ploughing 
April 2018 -  Registered (Sale Deed)
April 2018 -  Survey Stone Laying
February 2018 -  Sale Agreement
January 2018 -  Identified / Short Listed
August 2017 -  Agriculture Land Search